Enter a miracle
February 10 2025
The first instalment of the money arrived on March 5, and renovations began in earnest. Work began on the Winston V. Saunders theatre as soon as we could mobilize. First up: repairing the bathroom roof which had been damaged three years earlier in Hurricane Isaias. And we couldn’t repair the roof without refurbishing the bathrooms, could we? So the bathrooms were completely gutted.
Good thing, too, it turned out: they were harbouring four termite nests between them! Check out some of the progress below: